Use:-

You can use revisions to collect larger service or maintenance tasks under one number.
You enter a revision number in a notification or in an order and use it to summarize several notifications or orders.

Integration:-

The revision is connected to the status management and change documents.

You can enter the following data in a revision:

    Start and end of a revision
    Functional location
    WBS element or network

You can only assign a revision to a notification or an order if it has the status opened or released. You can then only close it if the assigned notifications or
orders are closed. If a revision has the status opened you can only directly close or delete it if no notifications or orders are assigned to it.

Notification and Order Processing

If you enter a revision when creating or editing an order, the dates in the revision are copied to the order. The same applies if:
(a) you create a notification from an order or
(b) you are creating a notification and you enter a revision at the same time as you create an order.

If you are editing a notification and enter a revision retrospectively, a dialog box appears. You must then decide if you want to copy the dates from the revision
to the notification.
Some notifications contain a revision and have been assigned to an order via an object list. You can delete these notifications from the order object list at anytime.

Checks

The system carries out various checks in the notification and in order processing.
You can make settings in Customizing to control how the system should react:

        If you assign notifications to an order, the system checks whether the revisions from the notification and order are the same.
    If not, the system will check whether they are allowed to differ.
        You create a revision for a specific functional location and enter the revision in a notification or order.
    A functional location is also entered as the base object in the notification or order. The system checks whether the base object
    (from the notification/order) is installed in the functional location structure (from the revision) or if it is identical.

    If you are processing a revision, the system will also check whether the revision is already assigned to a notification or order.
    The system then checks to see if a functional location has been entered in the notification/order.

        If the revision is assigned and no functional location has been entered in the notification/order, you can enter a functional location as a reference object in the revision.
        If the revision is assigned and a functional location has been entered in the notification/order, you cannot enter data in this field of the revision.

    You create a revision for a network and enter the revision in an order. A network is also entered in the order. The system checks whether the network (from the order) is contained in the network structure (from the revision).

The system carries out a similar check if a WBS element has been entered in the revision and in the order. However, in this case you cannot use Customizing to set the message, and you must decide whether you want to copy the WBS element from the revision to the order.

Saturday, November 27, 2010

Difference between Refrence functional Location and Functional Location

Reference Functional Location is a logical functional location and not a physical functional location.
It can be used to create several similar functional location.

Role of Maintenence Plan Categories

Maintenance Plan categories determine which call object (order, notification) the system generates for a maintenance plan when a maintenance call is due.

The call objects are
1- Maintenance or service order
2- Service entry sheet
3- Notification
4- Inspection Lot.

Difference Between Maintenence Plant and Planning Plant

Maintenance Planning Plant

The maintenance planning plant for a technical object is the plant in which the maintenance tasks for the object are planned and prepared. Maintenance planner groups work at the maintenance planning plant to plan and prepare the maintenance tasks for the plants that are assigned to the maintenance planning plant. The following activities are performed at the maintenance planning plant:

* Definition of task lists

* Material planning based on bills of material in task lists and orders

* Management and scheduling of maintenance plans

* Creation of maintenance notifications

* Execution of maintenance orders
The way in which you represent the organization of maintenance planning in your company depends on the structure of the entire company. You have three options:

* Centralized maintenance planning
* Decentralized maintenance planning
* Partially centralized maintenance planning

Centralized Maintenance Planning
Plants:0001, 0002, 0003
Maintenance plants:0001, 0002, 0003
Maintenance planning plant:0001
Plants assigned to the maintenance planning plant:0002, 0003

Decentralized Maintenance Planning
Plants:0001, 0002, 0003
Maintenance plants:0001, 0002, 0003
Maintenance planning plants:0001, 0002, 0003

Partially Centralized Maintenance Planning
Plants:0001, 0002, 0003, 0004, 0005
Maintenance plants:0001, 0002, 0003, 0004, 0005
Maintenance planning plants:0001, 0004
Plants assigned to maintenance planning plant 0001:0002, 0003
Plants assigned to maintenance planning plant 0004:0005

Tuesday, May 18, 2010

Can I maintain two different units in a measuring point?

You will need to create another measurement type
(characteristic) to accommodate the other unit of measure.
Create a new measurement point with a new unit of
measure and then link the new point with the old one using
transmission of measurement reading.

Process for maintaining Catalog profile for Equipment

Create a catalog profile and assign it to your equipment in the
Organization tab. This will then be copied to the Notification when the equipment number is entered.The same works for Functional locations.

Monday, May 17, 2010

Transaction Code is SAP PM

IA07 Display General Task List 
IA03 Display Equipment Task List 
IA13 Display Functional Location Task List 
IR03 Display Work Center 
KO88 Settle Order (Single) 
IW32 Change Work Order 
IW31 Create Work Order 
IW33 Display Work Order 
IW38 Work Order List Editing - Change 
IW39 Work Order List Editing - Display 
IW40 Work Order List Editing - Display Multi Level 
ME21 Create Purchase Order (pre R4.6) 
ME21N Create Purchase Order (R4.6 onwards) 
IP41 Create Single Cycle Plan (R4 onwards) 
IE02 Change Equipment 
IE01 Create Equipment 
IE03 Display Equipment 
IE05 Equipment List Editing - Change 
IE08 Equipment List Editing - Display 
IW42 Overall Completion Confirmation 
IW26 Create Notification 
QS42 Display Catalog 
ML81 Create Service Entry Sheet 
MM03 Display Material 
CS03 Display Material BOM 
IW13 Material Where Used List 
IW66 Change Notification List of Tasks 
IW67 Display Notification List of Tasks 
IW22 Change Notification 
IW23 Display Notification 
IH01 Display Functional Location Structure 
MB11 Goods Movement 
MB31 Goods Receipt 
IW8W Goods Receipt for Refurbishment (R4 onwards) 
IP02 Change Maintenance Plan 
IP03 Display Maintenance Plan 
IP10 Schedule Maintenance Plan 
IP30 Deadline Monitoring 
IP11 Change Maintenance Strategy 
IP12 Display Maintenance Strategy 
IP19 Maintenance Scheduling Overview Graphic 
IP24 Maintenance Scheduling Overview List 
IW28 Notification List Editing - Change 
IW29 Notification List Editing - Display 
IW30 Notification List Editing - Display Multi Level 
IW64 Change Notification List of Activities 
IW65 Display Notification List of Activities 
IW68 Change Notification List of Items 
IW69 Display Notification List of Items 
IQ03 Display Serial Numbers 
IW24 Create Notification 
IP42 Create Strategy Maintenance Plan (from R4 onwards) 
IW25 Create Notification 
IL02 Change Functional Location 
IL01 Create Functional Location 
IL03 Display Functional Location 
IL05 Functional Location List Editing - Change 
IL06 Functional Location List Editing - Display 
IW41 Time Confirmation - Individual Entry 
IW48 Time Confirmation - Collective Entry with Selection 
IW44 Time Confirmation - Collective Entry no Selection 
IA11 Create Functional Location Task Lists 
IA12 Change Functional Location Task List 
IL02 Change Functional Location 
IA05 Create General Task List 
IA06 Change General Task List 
IA01 Create Equipment Task List 
IA02 Change Equipment Task List 
IE03 Display Equipment 
IR01 Create Work Center 
IR02 Change Work Center 
CA85 Replace Work Center 
IP13 Strategy Package Sequence 
IP14 Strategy Package Sequence 
IP04 Create Maintenance Item 
IP05 Change Maintenance Item 
IP06 Display Maintenance Item 
IP17 Maintenance Item List Editing - Change 
IP18 Maintenance Item List Editing - Display 
IP02 Change Maintenance Plan 
IP03 Display Maintenance Plan 
IP15 Maintenance Plan List Editing - Change 
IP16 Maintenance Plan List Editing - Display 
IK11 Create Measurement Documents 
IK12 Change Measurement Documents 
IK13 Display Measurement Documents 
IK22 Measurement Documents List Editing - Create 
IK21 Measurement Documents List Editing - Create 
IK22 Measurement Documents List Editing - Create 
IK18 Measurement Documents List Editing - Change 
IK17 Measurement Documents List Editing - Display 
IK41 Measurement Documents List Editing - Display Archive 
IQ01 Create Serial Numbers 
IQ02 Change Serial numbers 
IQ04 Serial Numbers List Editing - Create 
IQ08 Serial Numbers List Editing - Change 
IQ09 Serial Numbers List Editing - Display 
IK01 Create Measurement Point 
IK02 Change Measurement Point 
Ik03 Display Measurement Point 
IK08 Measurement Point List Editing - Change 
Ik07 Measurement Point List Editing - Display